Maloyaroslavets Instrumental Plant, OJSC
Currently the plant is operating; there is possibility of the capacities’ utilization, lease of the area and other types of cooperation negotiable
Location
Western part of Maloyaroslavets
Land plot area – 97177,6 m2
Development area – 24319,4 m2
Transport accessibility
Distance to Kievsky highway – 7 km
Distance to Kalujsky – 0,6 km
Distance to the railway station – 3 km
Power supply
Power generation unit with 2 (main and reserve) cables of 10 KV voltage, power supply category - II.
Heat supply
Own gas boiler (can work on black oil) with 2 steam boil engines. Capacity - 40 tons of steam per hour or 35 Gcal/hour.
Water supply and drainage
From the network of the local water supply company and the well on the territory of the plant of 436,06 m3/day capacity. If necessary the well can fully cover the water needs.
Drainage system comprises
fecal and storm water discharge systems with discharge to the municipal
collectors.
Treatment facilities
Capacity - 231 m³/day.
Local treatment facilities with reactant way of treatment for galvanic
flow neutralization for the water containing acids, alkalis and heavy
metal salines. The treated water is discharged to the municipal sewage.
Treatment facilities
for storm water with the mechanical way of treatment are intended for
storm and melted water from the territory of the plant. Capacity –
30 l/sec. The discharged water goes to the river.
Water intake
Water intake on the
territory of the plant, comprises one well ¹12. Depth - 100 m.
Compressed air supply
Compressed air for production needs comes from 3 compressors in the power-generating unit (work pressure 8 atmospheres).
Exhaust control
Central certified laboratory on the territory of the plant provides exhaust control as well as ecological control and control over labour conditions on the plant.
Contacts
249091, Radishev Street, 8, Maloyaroslavets, Kaluga Region
Phone: (48431) 2-67-82, Fax: (48431) 2-67-62,
E–mail: mpz_office@kaluga.ru